Self-build home: Prepare production information
Introduction.
In this stage, we attribute design activities to ‘designers’. These may be architects and engineers, a design and build contractor, or a kit house supplier. If a kit house supplier is only supplying the house itself, additional design consultants may be required.
Production information is '...the information prepared by designers, which is passed to a construction team to enable a project to be constructed'.
The designer should develop a schedule of production information, responsibilities for its preparation, a programme for its preparation and a document control system for version control.
Production information may include:
- Drawings (location drawings, component drawings and dimensioned diagrams).
- Specifications, calculations and design criteria. Specifications provide descriptions of the materials and workmanship required. Design criteria might include; environmental conditions, acoustic requirements, critical dimensions, accessibility requirements, loadings and so on.
- Bills of quantities or schedules of work. Bills of quantities are measured quantities of the work identified on the drawings and specifications that can be used to cost the works. Schedules of work are 'without quantities' instructional specifications often produced on smaller projects, or for items such as builders work or fixing schedules.
There should be a particular emphasis on equipment with long lead time times that could delay the project, such as:
- Bespoke cladding systems.
- Service diversions.
- Demolition.
- Underground drainage.
- Piling and groundworks.
Preliminary contracts might be considered for some of these works to allow them to begin early. Long-lead items such as piling rigs might also be ordered in advance of other works.
The quality of production information is extremely important. Unless it is prepared and co-ordinated properly, there will be disputes and delays on site, and costs will be incurred.
Many elements of production information will be produced by suppliers or contractors. The designer should check drawings and specifications provided by suppliers and contractors to ensure they are properly co-ordinated.
Increasingly, software is used to prepare elements of production information, such as; computer aided design (CAD) to prepare drawings, and proprietary systems for the preparation of specifications. The recent emergence of building information modelling (BIM) can allow the automatic generation of production information from a single co-ordinated model, which should result in a reduction in errors and so costs.
NB During this stage, the lead designer should also co-ordinate any outstanding information needed for remaining building regulations or other statutory approvals which must be submitted before works start on site. It is also important to ensure that any necessary party wall notices have been served.
Next stage:
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Your guide to The Construction Reset at UKCW Birmingham.
Accommodating the Victorian and Edwardian working woman. Book review.
Rethinking passive fire protection in design
PFP demands the same level of design rigour as structure or services.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.
Communities will be able to build their own clean energy.
Why diversity and inclusion matters for SMEs
CIOB’s D&I Charter shows how practical changes can support long-term growth.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.